Work is progressing on the Multi-Faith Bathrooms and is tentatively scheduled to wrap up on Monday October 17th with the Women’s and Men’s washrooms opening shortly after. Work that will be done between October 7th and October 17th include:
October 6/7 – repairing substrate
October 11/12 – applying topcoat and waterproofing
October 13 – testing plumbing and waterproofing and tiling if testing successful
October 14/15 – applying grout and letting cure
October 17 – reinstalling toilets and cleaning up
The Ryerson Student Centre is eager to finish up this work and return the bathrooms to normal operation.